MS Project New Installation

J

jmac60

Hello,
Do you have or point me to an mpp template with general tasks, durations,
components and costs for a vanilla install of MS Project Server?
Thanx
John
 
R

Rick Roszko

Project Server questions should be posted in the Project Server forum...

As to your question, there was one a long time ago but it was so
generic, it would have taken longer to clean the plan up that to
install Project Server.

What is a vanilla install? For home use to try it out on a desktop PC?
A small company with one server? two servers? more?

Hint: If you know how to install MS Project Server, it takes 4 hours
in any configurtion you can think of. If you never installed Project
Server, it will take you at least 4 weeks+ because you will install
it incorrectly at least half a dozen times.

What!? Only 4 hours? Okay, That's like saying I just installed
"Windows 2003 Server". Now you have to configure it so people
can acually use the server, like permissions and such, right?
Well, MS Project is a bit harder to do...

If you (a) are not a "good" project manager, (b) never used MS
Project, and (c) don't know the difference between "Work" and
"Duration", your post-installation tasks will be next to useless.

Quickly, here are the tasks (2 server minimum recommended)
and this is no means complete!

4 hours:
- Install Windows Server 2003
- Install IIS6
- Configure IIS6
- Install Decision Support Objects
- Load Service Packs

4 hours:
- Install WIndows Server 2003
- Install SQL 2000
- Install Analysis Services
- Load Service Packs

4 hours:
- Install SharePoint Services
- Install MS Project Server

XX weeks:
- interview your users: PMs, Users,

??weeks training

??weeks (test):
- Configure PWA
- Configure Enterprise Global
- Load Enterprise Resource Pool

??weeks training

??weeks (pilot):
- Re-Configure PWA
- Re-Configure Enterprise Global
- Re-Load Enterprise Resource Pool

??weeks training

??weeks (limited rollout):
- Re-Re-Configure PWA
- Re-Re-Configure Enterprise Global
- Re-Re-Load Enterprise Resource Pool

??weeks training

??weeks (rollout):
- Re-Re-Re-Configure PWA
- Re-Re-Re-Configure Enterprise Global
- Re-Re-Re-Load Enterprise Resource Pool

Not done yet...

Have you read all of the problems these people are
having on this forum?

Avoid their errors!!!

Have a PRODCUTION system

Have a PRE-PRODUCTION system
- Replicate problems and tinker with settings here
so PROD doesn't need to go down each time a
problem occurs.

Have a TEST system
- Hear the horror stories on going to the next SP?
If you have a test system, you can try before
you move *any* SP to PROD.

Again, timeframe is soley dependant on the knowledge
and skill level of the installer for "pre-", "during" and
especially all of the "post-" installation of the product.

Thanks...
 
J

jmac60

Thanks, Rick...
Trying to put a rough budget together for an MSProject Pilot program.
I've configured servers & set up Web Access, but the server was up &
running. The guy before me couldn't get it to work. I got it to work, but the
developers wouldn't use it. No AD or outlook...what a fiasco.
So it's a couple of days for the installation, a month to configure access
rights, groups, & reports.
Ball park on software & hardware...basic stuff. $5,000, $10,000?
ciao
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top