MS Project

M

MichMoch

How to I assign a regular expense such as accomodation charges for workers
that will be staying away all week but who wish to return home on Fridays?
 
J

John

MichMoch said:
How to I assign a regular expense such as accomodation charges for workers
that will be staying away all week but who wish to return home on Fridays?

MichMoch,
Say what? This sounds more like an ethical question for the employee's
supervisor rather than a question about Microsoft Project. If this IS a
question about Project and you want help, you will have to explain it a
whole lot better.

John
Project MVP
 
M

Manmeet Chaudhari

Hi
There are 2 ways in which this can be done
1. Make use of cost rate table and give specific cost for a specific date
range
2. You can also use fixed cost for those taks which are getting affected
with the worker cost

Hope this helps
 