MS Standard Calendar Issue.

I

Imran

Hi,

i have created a project plan. now when i try to save it on server it gives
me message

"Enterprise standard calendar needed.

Enterprise standard calendar are required to:

Build a team for non-enterprise project
Save a non-enterprise project into the server.
Import resources to the enterprise.

This may result in changes to schedules date. Do you want to continue? "

and if i Press Yes then it changes Duration, Start, Finish date of many tasks.

i have tried it but unable to save my own project plan without any change.

can anyone tell me that wt is the issue. and wts wrong going on?

Thanks.

Imran
 
P

Projectability

Imran,

It sounds like the local settings you have are out of synch with the
Enterprise Standards. Check the following.

Tools>Change Working Time - check the hours per day and per week.
Tools>Options>Calendar - do your start time, end time, hours per day and
hours per week match those in the Standard Calendar?

--
Dominic Moss

Projectability - Helping People achieve more with Microsoft Project

Check the Downloads section on our Website for useful documents on both
Project Management and Microsoft Project

www.projectability.co.uk

Why not subscribe to our monthly newsletter for hints tips and views

http://visitor.constantcontact.com/manage/optin/ea?v=001WVdpo956d6lHqIISFtfgVw==
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top