i1. Open MSP
2. Create 2 activities (task 1 & task 2), set both durations to 10 days and
link them Finish-to-Start
3. Set the Task Type of both activities to Fixed Duration (highlight both
activities, shift-F2, Advanced tab, Task Type) then click OK
4. Reduce the duration of task 1 to 3 days and you will see that task 2
splits, keeping the end date fixed (same happens for all successive
activities). I don't see the problem when the Task Type is set to Fixed Work
or Fixed Units.
Has anyone else seen this problem (only seen in 2007 Beta).
Mark
2. Create 2 activities (task 1 & task 2), set both durations to 10 days and
link them Finish-to-Start
3. Set the Task Type of both activities to Fixed Duration (highlight both
activities, shift-F2, Advanced tab, Task Type) then click OK
4. Reduce the duration of task 1 to 3 days and you will see that task 2
splits, keeping the end date fixed (same happens for all successive
activities). I don't see the problem when the Task Type is set to Fixed Work
or Fixed Units.
Has anyone else seen this problem (only seen in 2007 Beta).
Mark