MSProject Gantt timescale not saved

A

ASpillert

I updated a plan in MSProject 2003 SP2 and saved it with a timescale
displayed (smallest increment) in weeks. When I reopen the project the
smallest timescale unit is days.

How can I keep the timescale consistent for my project from session to
session?

Thank you for any assistance.
 
C

Chris Marriott

Hi

Is the project an enterprise project using an enterprise view e.g.
enterprise gantt


If so your changes wont be saved... this is one of the changes you are not
warned about not being persistent ... if you added a column for example, a
dialog box would warn you that your changes would not be saved ... not the
case for scale changes

If you make a scale change in a local view e.g. the Gantt view this should
be persistent between including enterprise projects

I hope this helps
--
Regards


Chris Marriott - PMP MCSE MCDBA
UK - EPM Consultant & Trainer
 
A

ASpillert

Thank you - that is what is happening. It is an enterprise project stored in
Project Server 2003.
 
M

Mike Glen

Hi Chris,

Next time try posting on the server newsgroup. Please see FAQ Item: 24.
Project Newsgroups. FAQs, companion products and other useful Project
information can be seen at this web address:
http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top