J
Jens
Here is my problem.
When you enter work effort in days, project calulates an hourly effort based
on the project calendar. So, if the project calendar allows for 8 hrs per
day, and I assign a resource with a 24 hr calendar 1 days worth of work,
project calculates the finish date 1/3 day after thew start date.
I would like to enter work effort in days, but I would want to set up
multiple project calendars so that a day for an 8 hr resource is 8hrs, and a
day for a 24 hr resource is 24 hrs.
Is this possible?
Thanks
Jens
When you enter work effort in days, project calulates an hourly effort based
on the project calendar. So, if the project calendar allows for 8 hrs per
day, and I assign a resource with a 24 hr calendar 1 days worth of work,
project calculates the finish date 1/3 day after thew start date.
I would like to enter work effort in days, but I would want to set up
multiple project calendars so that a day for an 8 hr resource is 8hrs, and a
day for a 24 hr resource is 24 hrs.
Is this possible?
Thanks
Jens