multiple resource sheets?

M

Mike Johnston

Hi there. I'm trying to setup something in project that
will allow me to schedule a "deployment analyst" to work
on a "user".. however, I cannot figure out how to have
more than one resource sheet. Is this possible? If so,
how... if not, is there another way I can do this?
 
R

Rod Gill

Hi,

There is only one resource sheet. Enter your analyst and user on it and in
the Gantt chart assign them both to the same task.

--
Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA
development services
visit www.projectlearning.com/
 

Ask a Question