Multiple resources beginning same task at different times

R

rwhrangers

Is there a way. other than using subtasks for each resource. to have a single
task have 3 or 4 resources beginning and ending at different times and show
properly on the charts? Split task doesn't do it.
Thanks
 
J

Jan De Messemaeker

Hi,

It depends what you call "the charts"
Gantt Chart won't do it.
You will be able to see it properly in the task Usage view
There you can also enter contoured work or work with the assignment
information (ouble-click on an assignment line)

HTH
 