Multiple resources for a task

J

JoeW

I assigned 3 people to work on the same task lasting 5 days, but when I go to
the resource sheet view, 2 of the 3 people show their tasks as lasting 4
days. The other person had the task show up correctly as lasting 5 days.
What am I doing wrong?

thanks
 
J

JulieS

Hi JoeW,

Do the two resources have non-working time in their calendar? Double
click on the Resource Name in the resource sheet and click the working
time tab in the Resource Information dialog box.

Are the three resources assigned at the same assignment unit? From the
Gantt chart view split your screen (Windows > Split) to view the Task
Form at the bottom of the screen to view the resource assignment units
and work.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 
M

Mike Glen

Hi Joe,

Welcome to this Microsoft Project newsgroup :)

You might like to have a look at my series on Microsoft Project in the
TechTrax ezine, particularly #10 on multiple resource assignments, at this
site: http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the article before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 