G
Gavin
Quick query.
I have two guys (resources) working part-time (50%) on one
task. One of them is on vacation (nonworking time) for
part of the task duration. Project calculates the duration
as if no work takes place during the vacation period, even
by the guy who is still around (and whose calendar shows
default working hours).
i.e. 2 man-day task, starts Monday. Both guys work Monday
(guy A 0.5 man-day, guy B 0.5 man-day), guy A is on
vacation Tuesday but Guy B works (guy A 0, guy B 0.5 man-
day), same Wednesday (guy A 0, guy B 0.5 man-day). That
makes 2 man-days and the task is complete, with a duration
of 3 days. However Project puts the duration at 4 days,
with both guys working on Thursday (guy A having returned
from vacation).
Any advice to get around this would be greatly appreciated.
Gavin.
I have two guys (resources) working part-time (50%) on one
task. One of them is on vacation (nonworking time) for
part of the task duration. Project calculates the duration
as if no work takes place during the vacation period, even
by the guy who is still around (and whose calendar shows
default working hours).
i.e. 2 man-day task, starts Monday. Both guys work Monday
(guy A 0.5 man-day, guy B 0.5 man-day), guy A is on
vacation Tuesday but Guy B works (guy A 0, guy B 0.5 man-
day), same Wednesday (guy A 0, guy B 0.5 man-day). That
makes 2 man-days and the task is complete, with a duration
of 3 days. However Project puts the duration at 4 days,
with both guys working on Thursday (guy A having returned
from vacation).
Any advice to get around this would be greatly appreciated.
Gavin.