C
Chris B
I need to assign multiple resources to a task that requires that all the
resources work together in order to do any work. As an example.
A big screen television needs to be moved up a flight of stairs. Assigned
to the task are the resources Bob, Frank, and Julie. All three are needed to
move the TV and all are needed to be present and working at the same time to
complete the task. The total time needed to move the television is 20
minutes. All of this needs to be schedule around the normal work schedule of
all three and completed before a set time.
Using Units for work:
Normally if I were to assign multiple resources to the task at 100%
utilization, the allocation of the work would have Bob working for 10 minutes
and both Frank and Julie working for 5 minutes each to complete. This goes
against the concept of all three working together.
Using Duration for work:
At 100% utilization for all three, they all do 2 min of work, but they are
not scheduled to work at the same time.
how would I go about setting up the resources and task so that each of the 3
resources have simultaneous 20min assignments to do the task at 100% effort.
I've looked for quite a while and don't know if I missing something or
looking for something that isn't present. If this type a resources
allocation is missing then microsoft really needs to get back to reality.
resources work together in order to do any work. As an example.
A big screen television needs to be moved up a flight of stairs. Assigned
to the task are the resources Bob, Frank, and Julie. All three are needed to
move the TV and all are needed to be present and working at the same time to
complete the task. The total time needed to move the television is 20
minutes. All of this needs to be schedule around the normal work schedule of
all three and completed before a set time.
Using Units for work:
Normally if I were to assign multiple resources to the task at 100%
utilization, the allocation of the work would have Bob working for 10 minutes
and both Frank and Julie working for 5 minutes each to complete. This goes
against the concept of all three working together.
Using Duration for work:
At 100% utilization for all three, they all do 2 min of work, but they are
not scheduled to work at the same time.
how would I go about setting up the resources and task so that each of the 3
resources have simultaneous 20min assignments to do the task at 100% effort.
I've looked for quite a while and don't know if I missing something or
looking for something that isn't present. If this type a resources
allocation is missing then microsoft really needs to get back to reality.