minimadmark78 said:
Due to the nature of my project it is clearer to shedule everything form the
end date, however I have a problem when when using multiple start finish
dependancies.
example:
76 - Sample Ordering takes 10 days and needs to be done in advance of
77 - Board Fixtures which starts 09-aug and
78 - Tooling changes which starts 04-aug
I have used 77SF, 78SF which is giving me a start date of 09-Aug - what I
actually need is 04-Aug as samples need to be available for the earlier date
not the later for both to be achieved !
Can anyone tell me who I need to go about this?
You've run into a major problem with scheduling from Finish in Project.
It assumes that if you schedule from the finish date, instead of a
start date, that you want all tasks to start ALAP. Like in JIT delivery
in manufacturing. It sounds as if this is not the case in your
situation, as it isn't the case in most projects. You want, for most
tasks, just the opposite. Tasks to start as soon as possible, the
default condition when you schedule your project from the start date.
It also sounds as though you are worrying a lot about exact dates on
which the tasks must start and finish, and trying to use linking to
force pre-conceived dates for things to occur. And running into the
usual problems with this approach.
It's hard to explain online, but with CPM scheduling, it really makes
no difference whether you schedule from the start, or schedule from the
finish. The basic schedule will be the same, based on your task list,
estimated durations, and dependencies. So if you create the schedule,
and the duration is 200 days, does it really matter if you schedule it
to start tommorrow, and it shows it finishing 10 days later than the
deadline, or, you schedule it to finish by the deadline, which tells
you you should have started 10 days before tommorrow? Same predicament.
You have to shorten the schedule (attack the CP) by 10 days. Of course,
it you have 10 days extra, either way will show you that too. 10 days
extra is easier to deal with.
I suggest you reschedule your project scheduling from the start date,
then adjust as neccessary to get the finish date you desire. I think
you'll find it a little less problematic.
Hope this helps in your world.