W
Wendy
How is it that I can have a duration of 40+ days but my start and finish date
are either exactly the same or only a few days apart, and MSP sets the dates
to this when I change the duration?
Ultimately, here's what I'm trying to do...
I'm managing about 120 tasks, spread across about 8 different people. I
only get to utilize a couple hours of each person's time each week, so
initially I'm assuming I only get 5% of each person's time. My goal is to
figure out which tasks I can drive each week (as some require multiple people
to work on them) without overburdening anyone and guage the overall time to
complete all 120 items. As a starting point, I'd like to assume that each
task can be completed in about 1 week with the assigned resources, assuming
they have 5% of their time to give.
I realize this is a somewhat non-standard/inside-out use, but it's still my
job and I think project is capable of helping me visualize this...I just
can't figure out how.
As an example, I currently have a task with 1 person assigned at 1% (Units)
with a duration of 90 days, but the start date is 12/14 and the finish date
is 12/31. I've removed the Effort Driven constraint because it sounds like
something I wouldn't want to use and I've aslo made it a Fixed Duration task
type...though ideally my duration will only be about 5 days, and the total
work will be 2 hrs. Perhaps I'm not using Units correctly....but somehow i
need to assign people based off the percentage of their time that I can
comendeer over a given number of days and have the total hours fill in
automatically.
How do I do this?
Thanks!
are either exactly the same or only a few days apart, and MSP sets the dates
to this when I change the duration?
Ultimately, here's what I'm trying to do...
I'm managing about 120 tasks, spread across about 8 different people. I
only get to utilize a couple hours of each person's time each week, so
initially I'm assuming I only get 5% of each person's time. My goal is to
figure out which tasks I can drive each week (as some require multiple people
to work on them) without overburdening anyone and guage the overall time to
complete all 120 items. As a starting point, I'd like to assume that each
task can be completed in about 1 week with the assigned resources, assuming
they have 5% of their time to give.
I realize this is a somewhat non-standard/inside-out use, but it's still my
job and I think project is capable of helping me visualize this...I just
can't figure out how.
As an example, I currently have a task with 1 person assigned at 1% (Units)
with a duration of 90 days, but the start date is 12/14 and the finish date
is 12/31. I've removed the Effort Driven constraint because it sounds like
something I wouldn't want to use and I've aslo made it a Fixed Duration task
type...though ideally my duration will only be about 5 days, and the total
work will be 2 hrs. Perhaps I'm not using Units correctly....but somehow i
need to assign people based off the percentage of their time that I can
comendeer over a given number of days and have the total hours fill in
automatically.
How do I do this?
Thanks!