D
dsm
I was asked to take my project plan and show only the executable tasks in
chronological order. The kicker here is that I need to be able to get the
Task ID, Task Name, Duration, custom text fields, etc. into an Excel or Word
format so this can be listed on our SharePoint site.
There is a group that would like to keep that page open and only have to
refresh it to see where the current project status is for an implementation
project that is to occur over a 7 day period.
I need lots of help on this, because I can print a report that has exactly
what I want, but I can't get the data into an Excel or Word format.
Then the other way is to do a "Save As" for the Excel format, but it brings
over the summary tasks. I don't want to have to go through the workbook and
strip out all of the summary tasks because the detailed executable tasks are
not all at the same level in the project plan.
chronological order. The kicker here is that I need to be able to get the
Task ID, Task Name, Duration, custom text fields, etc. into an Excel or Word
format so this can be listed on our SharePoint site.
There is a group that would like to keep that page open and only have to
refresh it to see where the current project status is for an implementation
project that is to occur over a 7 day period.
I need lots of help on this, because I can print a report that has exactly
what I want, but I can't get the data into an Excel or Word format.
Then the other way is to do a "Save As" for the Excel format, but it brings
over the summary tasks. I don't want to have to go through the workbook and
strip out all of the summary tasks because the detailed executable tasks are
not all at the same level in the project plan.