Need Help With a Custom Equation/Indicator MS Project 2007

J

Jonathon

I am having issues writing a custom equation in MS Project 2007 that
can
put an indicator next to any task that is due from the current date to
+14 days forward. Does anyone have any experience with this?

Thanks In Advance,
Jonathon
 
J

Jack Dahlgren

should be pretty simple with an iif statement

This for example shows some text for any uncomplete tasks due within the
next 14 days. It also captures any which were overdue but you can modify
that by adding another condition

IIf([% Complete]<100,IIf([Finish]<([Current Date]+14),"This is due within 14
days",""),"")

-Jack Dahlgren
http://zo-d.com/blog
 