G
Graham J
I have a number of independent tasks that have been sized to take a certain
amount of effort each. I have a single resource that will be working on
these tasks simultaneously. Start dates cannot be delayed, so leveling can't
be used. I have flexibility to change the end dates for each task though. I
need to calculate these end dates when one resource is working on all these
tasks simultaneously.
Originally I've tried changing the resource's allocation to reflect the
number of tasks. e.g. with 5 tasks, I set the allocation to 20%. The
problem with doing this is that MSP assumes that the 20% allocation lasts for
the entire duration of each task. Each task has a different duration, so
there are times when there are 5 simultaneous tasks, and other times there
are 4, other times 3, etc. So assuming 20% allocation for the life of each
task isn't realistic. There will be times when I can allocate a resource 25%
(4 simultaneous tasks), and 33% (3 simultaneous tasks).
Is there a way that I can have the percentage allocation on each task
automatically change based on the number of simultaneous tasks? Is there any
other way I can calc end dates for this scenario?
amount of effort each. I have a single resource that will be working on
these tasks simultaneously. Start dates cannot be delayed, so leveling can't
be used. I have flexibility to change the end dates for each task though. I
need to calculate these end dates when one resource is working on all these
tasks simultaneously.
Originally I've tried changing the resource's allocation to reflect the
number of tasks. e.g. with 5 tasks, I set the allocation to 20%. The
problem with doing this is that MSP assumes that the 20% allocation lasts for
the entire duration of each task. Each task has a different duration, so
there are times when there are 5 simultaneous tasks, and other times there
are 4, other times 3, etc. So assuming 20% allocation for the life of each
task isn't realistic. There will be times when I can allocate a resource 25%
(4 simultaneous tasks), and 33% (3 simultaneous tasks).
Is there a way that I can have the percentage allocation on each task
automatically change based on the number of simultaneous tasks? Is there any
other way I can calc end dates for this scenario?