Need to force resources to work at the same time. ex: a meeting

E

Ed Berde

Task 1 (8 hours) requires equal commitment from two resources (A and B). A
has no assignments and is available to work on any day. B is available to
work only 1 hour each day.

Project assigns A to Task 1 for 4 hours on day 1. It assigns B to Task 1
for 1 hour a day for days 1-4. This is unrealistic since the resources need
to work together.

I would envision a checkbox or something in the resource assignments tab to
do this. Something like 'Resources must work concurrently'.

Is there currently any way to do this in Project?
 