Ed Berde
Task 1 (8 hours) requires equal commitment from two resources (A and B). A
has no assignments and is available to work on any day. B is available to
work only 1 hour each day.
Project assigns A to Task 1 for 4 hours on day 1. It assigns B to Task 1
for 1 hour a day for days 1-4. This is unrealistic since the resources need
to work together.
I would envision a checkbox or something in the resource assignments tab to
do this. Something like 'Resources must work concurrently'.
Is there currently any way to do this in Project?
has no assignments and is available to work on any day. B is available to
work only 1 hour each day.
Project assigns A to Task 1 for 4 hours on day 1. It assigns B to Task 1
for 1 hour a day for days 1-4. This is unrealistic since the resources need
to work together.
I would envision a checkbox or something in the resource assignments tab to
do this. Something like 'Resources must work concurrently'.
Is there currently any way to do this in Project?