New Project Server setup - Working Time help

E

ESmith

I'm setting up a new Project Server and I want to define a "working day" as
5 hours ( leaving the rest as slack for all the unknown things that pop-up).

What I'd like to see is that when I define a task, for example, as starting
on Monday and finishing on Thursday as having a duration of 4 days. I've
been unable to figure out how to get this to work. I've tried setting
creating a template where I say the working hours are from 8am to 1pm (or
2pm to account for an hour lunch break?) and the hours per day and week to 5
and 25 respectively. All combinations fail - the system seems to be
calculating my "4" example above based on an 8 hour day regardless that I've
defined hours per day as 5.

How can I setup project to accept that my work day is 5 hours and allow me
to define start/finish times that account for only the 5 hour work day?

Thanks!
 
D

Dale Howard [MVP]

ESmith --

Please do not cross-post your questions. I answered your question in the
Project Server newsgroup.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top