A
Adam Lipscombe
Folks,
I have several newbie questions:
I have a project with 15 summary tasks, each of which is comprised of many
smaller tasks.
1. I want to level resources, yet maintain the order in which the sumary
tasks are worked on. How do I do this?
2. Project Viewer.
Is there a free viewer available form Project 2003 files?
My team members only need to view the gantt charts and we cant afford to
buy Project for all of them.
TIA - Adam
I have several newbie questions:
I have a project with 15 summary tasks, each of which is comprised of many
smaller tasks.
1. I want to level resources, yet maintain the order in which the sumary
tasks are worked on. How do I do this?
2. Project Viewer.
Is there a free viewer available form Project 2003 files?
My team members only need to view the gantt charts and we cant afford to
buy Project for all of them.
TIA - Adam