A
aww91
Need help clarifying my understanding of overdue tasks.
When a task is overdue it turns red. Can someone explain what is
happening behind the scene for MS Project to make this determination?
I have almost two identical tasks and one is red while the other is not
and the differential seems to be the predecessor of one over the other.
Thank You,
When a task is overdue it turns red. Can someone explain what is
happening behind the scene for MS Project to make this determination?
I have almost two identical tasks and one is red while the other is not
and the differential seems to be the predecessor of one over the other.
Thank You,