Oh I know all about weekend work. Back in the 60's & 70's I worked in the
airline industry and I went for a 5 year stretch before I had enough
seniority to bid a shift with weekends off. What I was trying to say is
that people always have regularly scheduled working hours and it's smart to
only schedule project tasks during the normal working hours of the resources
doing it, whatever that may be. If it's important for work on a task to
take place on a weekend you assign the task to someone who's regular shift
includes weekends, not a M-F person on the hope they'll be willing to work
extra for you. Uttster seemed to be saying the resource in question worked
M-F but could be counted on working over the weekend, outside of their
normal working hours, if a task started too late in the week to finish
before the weekend arrived. I think it's extremely dangerous to your
schedule to assume they'll do that voluntarily and to build that assumption
into the offical plan and at the very least abusive of the worker if not
downright a violation of labour laws to mandate they do it involuntarily. I
take it as a given that one must always respect the dignity of the worker
and both the letter and the spirit of the law as the price of being allowed
to stay in the game, even if doing so means ther project's schedule is
longer and budget is higher than one might otherwise be able to achieve.
When I read your statement that you have a group that works 2 10-hour shifts
7 days a week I have to wonder when they rest. To me a "group" means all
members of the group work identical hours and days off. So when you say
that, I see people who work 20 hours per day and never get a day off and
that can't be real any place outside of the Gulag. Don't you mean you have
a group that works 10 hour day with sat sun off and another group that works
10 hour days with Mon Tue off and yet another that works 10 hour days with
Tue Wed off etc etc etc? I try to teach my classes that they need as a
minimum however many base calendars are required to cover every unique
combination of general working hours, days off, and stautory holidays that
the resources may have. I don't suggest necessarily a base calendar for
people who arrive at 8am and another for those arriving at 9am - resource
calendars can take care of those minor deviations - but if we cover 24/7 by
working day, swing and grave shifts, some people wth Fri Sat off, other with
Sat Sun off, and others with Sun Mon off and have some resources here in
Ontario and others next door in Quebec (different statutory holidays) you
have at the very least 18 calendars (3 basic shifts * 3 RDO patterns * 2
jurisdictions). Since I'm ultimately going to have to get the task
assignments detailed down to the point of assigning Joe who works 10am-7pm
with Wed Thur off to a task and the consequences to my schedule of that
assignment will be different than if I assign Bill who works 8am-5pm with
Sat Sun off, I can't just lump Joe and Bill together into a group that works
8am to 7pm 7 days a week when viewed in the aggregate even if they both
happen to have the same job skills and are otherwise interchangeable. I
have to split them out and when I assign resources I have to think whether I
should give the task in question to a guy with weekends off or to the guy
with mid-week days off.
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs