In MS Project does "non default working time" mean you choose hours other
than 9-5? I am looking at the general working time and I notice this.
 
J

Jack Dahlgren

Non-default working time is working time which is not the default - in
project the default time is 8-12 and 1-5 Monday through Friday.

So if you set a calendar with working time on Saturday or late hours on
Wednesday, that working time is non-default working time.

-Jack
 
T

Té

Thank you Jack!!!

Jack Dahlgren said:
Non-default working time is working time which is not the default - in
project the default time is 8-12 and 1-5 Monday through Friday.

So if you set a calendar with working time on Saturday or late hours on
Wednesday, that working time is non-default working time.

-Jack
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top