Tom123
Folks,
I'm a newbie to Project and I have some challenges using the application. I
have tried and read documentation but nothing seems to be working. That is
why I am sending this.
Scenario: I have tasks that bridge over weekends and instead of the system
to treat them as non working days, it takes them as working days. For
example, I have a task that is for 10 days and starts on 20th, Project tells
me it ends on 28th. That is even 9 days and it counts the weekend days.
All the tasks are using Project Standard calendar.
Thanks
I'm a newbie to Project and I have some challenges using the application. I
have tried and read documentation but nothing seems to be working. That is
why I am sending this.
Scenario: I have tasks that bridge over weekends and instead of the system
to treat them as non working days, it takes them as working days. For
example, I have a task that is for 10 days and starts on 20th, Project tells
me it ends on 28th. That is even 9 days and it counts the weekend days.
All the tasks are using Project Standard calendar.
Thanks