Null Value in Project (Task) View

T

Theresa

I am trying to build views and want to exclude Summary Tasks that do not have
a resource assigned to them. When I try to filter out “NULLâ€, “NAâ€,
“Unassignedâ€, or “4294967296†(We found this somewhere on the internet -
project creates this numerical value for blanks) I am still unable to filter
out the blanks. Any ideas?? I found a work around; using the logic Resource
Names begins with _ (the underscore character (_) to represent any single
character). I still am curious, in case we ever want to filter for that
blank value.

Thank you,

Theresa
 
N

NZ Projects

Theresa,

You should never assign resources to summary tasks as this will lead to all
sorts of problems when entering time and reporting task progress.

I cannot stress this enough.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top