Old project

B

blake williams

Is it possible to take an old project and use all the old tasks and just change the project start date, and use all the durations?? If so how?
 
P

pratta

Sure is.
Best to do a bit of preparation though.
File New - and set the project start date in Project/
Project Information.
Select all the old tasks and paste into the new file
The project will start from the Project Start Date you set.
I suggest making sure all tasks are - As Soon as Possible.
If you have a large # of tasks, an easy way to do this is
Insert / Column/ and select Constraint Type, and check,
and reset where necessary.
I would link all the tasks at this stage, being careful
not to include any summary tasks in the linking process.
You mentioned keeping the durations. If so insert a column
fo Type, and select fixed Duration. That make you the
master of Duration.
You haven't mentioned resources, but you can copy them
across no problems. Perhaps consider setting up a Calendar
to use as your base calendar.
Actually, you can do all this by saving your old schedule,
and just changing the Project Start Date in
Project /Project Info.
Hope this is what you were after.
-----Original Message-----
Is it possible to take an old project and use all the old
tasks and just change the project start date, and use all
the durations?? If so how?
 
J

Jan De Messemaeker

Hi,

The following is AFAIK the fastest way:

Select all tasks
Task Information Icon
Set % complete to 0

Now it depends on what you want to do with your old constraints.
If you do not want them to be taken into account, with task information open
set constraint to as soon as possible; then set Project Start to the new
start date and off you go

If you want to move them by the same number of days as the project start,
leave task infoemartion, show the analysis toolbar and click adjust dates.
Follow the instructions.

Good Luck

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/index.htm
32-495-300 620
blake williams said:
Is it possible to take an old project and use all the old tasks and just
change the project start date, and use all the durations?? If so how?
 