D
DianneZ
I have 6 tasks linked together, (one of these has a deadline).
These 6 are followed by a gap created by a SNET constraint on the 7th task.
The critical path is showing as starting from the 7th task. When I enter
actual data in the tracking table for one of the non critical tasks, (the one
with the deadline)… the task shows shows as red in the tracking gantt.
Can you explain why is does this when the tasks around it are still blue ?
Thank you,
DianneZ
These 6 are followed by a gap created by a SNET constraint on the 7th task.
The critical path is showing as starting from the 7th task. When I enter
actual data in the tracking table for one of the non critical tasks, (the one
with the deadline)… the task shows shows as red in the tracking gantt.
Can you explain why is does this when the tasks around it are still blue ?
Thank you,
DianneZ