R
RVW
ok, I've entered the task, go to window then split, type
in the resource name, go to details and highlight
resource cost. Enter fixed duration 0d and units 0%.
Then I entered the actual cost. This worked fine until I
tried to add another resource under the same task the
same way. The added cost is not being added into the
total cost of the task. any ideas?
in the resource name, go to details and highlight
resource cost. Enter fixed duration 0d and units 0%.
Then I entered the actual cost. This worked fine until I
tried to add another resource under the same task the
same way. The added cost is not being added into the
total cost of the task. any ideas?