K
Kandy
I want to track all activities that my company is working
on. Some are projects that have end dates, while others
are ongoing. I would like to have some ongoing activities
considered in the time for the projects, but I do not want
to assign a distant future end date, since that will push
out my timeline, nor do I want to use "0 days", since the
time would not be considered at all.
For example:
+ Task
Project A - 5 days
Project B - 3 days
Is there a way that I can have the time factored in,
without setting an end date? Please advise. Thanks.
on. Some are projects that have end dates, while others
are ongoing. I would like to have some ongoing activities
considered in the time for the projects, but I do not want
to assign a distant future end date, since that will push
out my timeline, nor do I want to use "0 days", since the
time would not be considered at all.
For example:
+ Task
Project A - 5 days
Project B - 3 days
Is there a way that I can have the time factored in,
without setting an end date? Please advise. Thanks.