Operation Failed

B

Bill

Hi All,

I have entered my cost data as fixed costs against milestones within the
project and now need to save the data to Excel.

I select the Task Usage - Costs view and go trough the Save As xls wizard
and get an 'Operation Failed'. I use the existing map for exporting 'cost
data by task'.

All I get is the error message. Anyone idea ideas please?

Ta.
Bill.
 
J

Jim Aksel

Of course updating to the latest service packs, etc. would not hurt.
Occassionally these add-ins need a kick in the pants to get them to work
correctly.

Go to my website, link below. Click on MS Project Tips on the left side. I
have a procedure of how to re-add the COM Add Ins at the bottom of that
page. It links to a pdf file with screen shots, etc. See if that helps.
--
If this post was helpful, please consider rating it.

Jim

Check out my new blog for more information:
http://www.msprojectblog.com
 
B

Bill

Thanks Jim, before reading this I had updated to SP3 across the board and
then the security tab in Project allowed me to configure appropriately.
Regards.
Bill.
 