1969 Project Genesus
Is it possible to create an "optional task" in Microsoft Project?
Example 1:
You have been assigned to procurement equipment to get a lab station set up
within some time period.
The following tasks are included:
Lab Readiness
1) Acquire Computer
2) Acquire Monitor
Optional Enhancements:
a) Acquire LCD Monitor
Using BBS techniques (beg, barrow, steal) you get the lab station set up to
work with an computer and old CRT monitor. At some time in the future you
will acquire the LCD monitor, but the “Lab Readiness†task can be considered
complete since the station is available for the engineers to start.
You have a task to get a software CM (configuration management) tool setup
on the same lab station mentioned previously.
Example 2:
Software Installation
Get CM Tool for lab station
Expensive CM tool (may take weeks/months)
Optionally use Microsoft Source Safe
It has been determined (outside of your control) that the lab station will
use a particular CM tool that has been purchased, but your not going to have
your team of engineers wait around for months and decide to utilize another
product (such as Microsoft Source Safe) in the meantime.
Example 1:
You have been assigned to procurement equipment to get a lab station set up
within some time period.
The following tasks are included:
Lab Readiness
1) Acquire Computer
2) Acquire Monitor
Optional Enhancements:
a) Acquire LCD Monitor
Using BBS techniques (beg, barrow, steal) you get the lab station set up to
work with an computer and old CRT monitor. At some time in the future you
will acquire the LCD monitor, but the “Lab Readiness†task can be considered
complete since the station is available for the engineers to start.
You have a task to get a software CM (configuration management) tool setup
on the same lab station mentioned previously.
Example 2:
Software Installation
Get CM Tool for lab station
Expensive CM tool (may take weeks/months)
Optionally use Microsoft Source Safe
It has been determined (outside of your control) that the lab station will
use a particular CM tool that has been purchased, but your not going to have
your team of engineers wait around for months and decide to utilize another
product (such as Microsoft Source Safe) in the meantime.