K
Karen
For a FIXED WORK schedule, is there a best practice associated with the order
in which the schedule initially gets created? In other words, once my tasks
and sub-tasks are put into the schedule, should I then populate 1) resource
name, 2) predecessors, and 3) work? Or is there a better order to enter
those pieces of information?
Thanks,
Karen
in which the schedule initially gets created? In other words, once my tasks
and sub-tasks are put into the schedule, should I then populate 1) resource
name, 2) predecessors, and 3) work? Or is there a better order to enter
those pieces of information?
Thanks,
Karen