Hi Jeff,
As John noted, there are only a few fields that carry from the Resource
side of Project to the Task side of Project. If you entered information
into the Group field on the Resource sheet, that information can be
displayed in the Task Sheet (left side of the Gantt Chart view) by
adding the field Resource Group. The Resource Group field added to the
Gantt Chart View is read only but will display the group for each
resource *assigned* to the tasks. You will only see the group
information when a resource from that group is assigned to the task.
You can also use the Phonetics field added to the Resource Sheet and
displayed in the Gantt Chart view by adding the Resource Phonetics
field. Again, it will only show information for resources assigned to
the task.
For additional information, see FAQ #51 at:
http://project.mvps.org/faqs.htm
I hope this helps. Let us know how you get along.