other projects and commitments total is not correctly adding subto

M

Michael @ BLITZ

i'm looking in the Resource Usage view. I have a resource that has 2 tasks
under Other projects and commitment totaling 4 hours of work.

However, looking at the other projects and commitment line it's not totaling
it up as 4 it's showing another number.

Why is this? Why doesn't the other projects and commitment line correctly
add up all the child tasks it has below it?

Michael
 
C

chickenmcnoggin

i'm looking in the Resource Usage view. I have a resource that has 2 tasks
underOtherprojectsand commitment totaling 4 hours of work.

However, looking at theotherprojectsand commitment line it's not totaling
it up as 4 it's showing another number.

Why is this? Why doesn't theotherprojectsand commitment line correctly
add up all the child tasks it has below it?

Michael

Michael,

I am also experiencing this problem, have you come up with any more
information?

Thanks,

Brian
 
M

Mike Glen

Hi Michael,

Welcome to this Microsoft Project newsgroup :)

What version of Project are you using? And the Service Release number? Are
you using Project Server?

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top