J
Jitesh
Hi guys and gals
First time poster been ready all your useful hints and advise.
Two things i need help with:-
1) Is it possible to have dates that are already within an outlook calender
to be input automactically into project?
What i am trying to do is set up a project where the dates for approval
meetings have been inputed ito outlook i wanted project to look up when that
date is for that week and have the task set for that date.
2)The project is finish date based and the penultimate task is always 3
months before the ship date which is 1st of a month but the penultimate task
is also the 1st of the month ie is the end task is 1 dec 2005 the penultimate
task is 1sept also this is as you see is not exatly a set number of days it
can vary from month to month depending on the number of days in the month. is
is possible to automate this too that project sets the date to the begining
of that month
I hope that makes sense
Thanks in advance
Jitesh
First time poster been ready all your useful hints and advise.
Two things i need help with:-
1) Is it possible to have dates that are already within an outlook calender
to be input automactically into project?
What i am trying to do is set up a project where the dates for approval
meetings have been inputed ito outlook i wanted project to look up when that
date is for that week and have the task set for that date.
2)The project is finish date based and the penultimate task is always 3
months before the ship date which is 1st of a month but the penultimate task
is also the 1st of the month ie is the end task is 1 dec 2005 the penultimate
task is 1sept also this is as you see is not exatly a set number of days it
can vary from month to month depending on the number of days in the month. is
is possible to automate this too that project sets the date to the begining
of that month
I hope that makes sense
Thanks in advance
Jitesh