J
Jeff Chapman
Hello all - I work with Project 98, and I've been having a
real whale of a time trying to get my Gantt chart outputted
the way that I want it. I want to paste a Gantt chart for a three-month
span into a Visio 2002 file. I have tried Copy Picture (for
screen, print, and to file), outputting to PDF and then
copying/pasting the relevant section into Visio as an
Enhanced Metafile, and more.
The main problems I have been having:
- the Task Name column gets cut off when using Copy as Picture
- the image resolution of GIF output looks poor when printed
- the month names in the timescale get cut off
- the size of picture data when pasted into Visio boosts the file size
up to 20MB (previously under 1 MB)
Does anybody know whether later versions of Project have better
and more robust image output and printing functions?
Thanks,
Jeff Chapman
real whale of a time trying to get my Gantt chart outputted
the way that I want it. I want to paste a Gantt chart for a three-month
span into a Visio 2002 file. I have tried Copy Picture (for
screen, print, and to file), outputting to PDF and then
copying/pasting the relevant section into Visio as an
Enhanced Metafile, and more.
The main problems I have been having:
- the Task Name column gets cut off when using Copy as Picture
- the image resolution of GIF output looks poor when printed
- the month names in the timescale get cut off
- the size of picture data when pasted into Visio boosts the file size
up to 20MB (previously under 1 MB)
Does anybody know whether later versions of Project have better
and more robust image output and printing functions?
Thanks,
Jeff Chapman