Overallocation of resources instead of changing dates

Z

Zazoo

I have one resource who is running 2 projects at a time. The only date
constraint on my projects is a "start as soon as possible" constraint. When I
allocate the resource on the projects, if there are some tasks which were
previously (i.e. before I assigned a resource) set on the same day, instead
of changing one date, Project makes my resource work 16 hours a day : 8h on
project A plus 8h on project B. What to I have to do for it to re-schedule
the projects?
Thank you.
 
M

Mike Glen

Hi Zazoo,

Welcome to this Microsoft Project newsgroup :)

You might like to have a look at my series on Microsoft Project in the
TechTrax ezine, particularly #19 & 29 on levelling, at this site:
http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the articles before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top