That's fine, but how many hours per day does his calendar say he works? The
assignment percentage is NOT the amount of his workday spent on each task -
I think of it more as an indicator of how fast he converts time into work
output. If his working day calendar says he works 10 hours in a day and he
has 2 tasks, one lasting 8 hours and the other lasting 2 hours, he is
working 100% on each. Since your original post referred to overtime,
though, perhaps we have a different issue. I am having a hard time getting
your numbers to add up though. If the resource was working on just one task
at a time and worked for just his normal 8 hours per day workday on just
those tasks, how long would it take him to complete each one? By the way,
0800 to 1600 isn't likely to be an 8 hour day unless the resources doesn't
take lunch - you really need to include the break allowance else your work
and durations will get out of sync by a very signifigant amount very
quickly. So if he's on the property from 0800-1600 and gets 30min for
lunch, thats 7.5 working hours, not 8, and your calendar really needs to
reflect that detail.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
Ionut said:
Dear Steve,
Thank you for your answer regarding my 120% allocation.
What I had in mind was that the person will work 10 hours a day, let us
say
8 hours for a task, from 8 to 16 and another 2 hours, from 16 to 18 for
the
second task. This is the situation I want to model.
Thank you in advance for your help,
Kind regards
Professor Ionut Lambrescu
Blvd Bucuresti nr. 39
Ploiesti 100680
Romania
Steve House said:
How can a resource be allocated 120%, at least if it's a single
individual
person? That means that somehow over the course of, say, 8 working hours
he
can magically accomplish what regular people would take almost 10 hours
to
accomplish. This is generally not an accurate depiction of reality.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
I have 2 activities, one lasts 3 days, the other 4 days. They overlap
for
two
days (days 2 and 3 of the first activity and 1 and 2 of the second). I
have
one resource, with 120% availability. This resource will be allocated
100%
to
the first activity, and 10% to the second. For the 2 overlaping days, I
want
that the resource be paid for the 10% alocated to the second activity
as
overtime. When I define the overtime work, even though initially the
work
spent by the resource over the 4 days of the second activity was evenly
distributed, it ends on one single day (as overtime). Is it possible to
spread it evenly over the 4 days of the second activity?
many thanks
Ionut Lambrescu