Jesse
I'm having a brain cramp trying to understand overtime work. If I have a
resource assigned to a 24 hr task over 3 days and that resources works 30 hrs
over 3 days then the resource has worked 30 hrs. Assuming that I want to
keep track of overtime work, should I enter that time for the resource as 24
hrs work and 6 hrs overtime work....or 30 hrs work and 6 hrs overtime work?
What affects does overtime work have?
resource assigned to a 24 hr task over 3 days and that resources works 30 hrs
over 3 days then the resource has worked 30 hrs. Assuming that I want to
keep track of overtime work, should I enter that time for the resource as 24
hrs work and 6 hrs overtime work....or 30 hrs work and 6 hrs overtime work?
What affects does overtime work have?