J
Jim19382
I need to set cost per day for resources where the full cost is charged for
each day of the task, whether the resource works 1 hour or 24 hours during
that day. I have set up a cost per diem custom cost field for a resource,
but can't figure out how to multiply the duration (in whole days) in the
tasks table by the custom field per diem cost in the resources table. I also
need to know how to make a custom cost field value be included in the total
cost for a task.
Thanks
Jim
each day of the task, whether the resource works 1 hour or 24 hours during
that day. I have set up a cost per diem custom cost field for a resource,
but can't figure out how to multiply the duration (in whole days) in the
tasks table by the custom field per diem cost in the resources table. I also
need to know how to make a custom cost field value be included in the total
cost for a task.
Thanks
Jim