4
4lane
Suddenly, none of my tasks are rolling up to their parent. It must be some
setting that I set, but it's impossible to figure out what it might be.
If you look at the screenshot, you'll see my test, where two subtasks rull
up to a main task. The main task should show a %Complete of X percent, the
Duration should show 15 days, the start date should show 12/1/2008, and the
end date should show 12/12/2008. Instead the main task just shows default
data that was originally entered. Also, you can normally edit the main tasks
% Complete, but as you can see from the screenshot, it is disabled.
Does anyone know what the problem is?
Screenshot:
http://files.engineering.com/getfile.aspx?folder=96e9929c-e9d6-43cf-b5a6-89ef310acb94&file=test.jpg
setting that I set, but it's impossible to figure out what it might be.
If you look at the screenshot, you'll see my test, where two subtasks rull
up to a main task. The main task should show a %Complete of X percent, the
Duration should show 15 days, the start date should show 12/1/2008, and the
end date should show 12/12/2008. Instead the main task just shows default
data that was originally entered. Also, you can normally edit the main tasks
% Complete, but as you can see from the screenshot, it is disabled.
Does anyone know what the problem is?
Screenshot:
http://files.engineering.com/getfile.aspx?folder=96e9929c-e9d6-43cf-b5a6-89ef310acb94&file=test.jpg