B
Brian Lukanic
What is a Best Practice for building in a phase-gate review in MS Project.
For example, I want to include a "go/no-go" decision point in the schedule.
The dilemma I face is whether to bake in the followon tasks for both decision
points.
Although a Project schedule should be deliverables-based and not
activity-based, our use of Project is actually to wrap actions around our
deliverables. Because of this, there are some deliverables that conclude with
a phase gate review. A "Go" decision would lead to a new set of deliverables
and tasks, while a "No Go" would lead to closure activities, documentation,
etc.
Although a chronology in Project is not recommended, I at least want to
build in these phase-gate reviews. When in planning the schedule, should I
simply design in the steps for either decision (go and no-go), and then when
tracking the decision actuals simply delete the follow-on tasks that were not
chosen?
Anyone who has used phase gates in MS Project I'd love to hear your thoughts
on this.
For example, I want to include a "go/no-go" decision point in the schedule.
The dilemma I face is whether to bake in the followon tasks for both decision
points.
Although a Project schedule should be deliverables-based and not
activity-based, our use of Project is actually to wrap actions around our
deliverables. Because of this, there are some deliverables that conclude with
a phase gate review. A "Go" decision would lead to a new set of deliverables
and tasks, while a "No Go" would lead to closure activities, documentation,
etc.
Although a chronology in Project is not recommended, I at least want to
build in these phase-gate reviews. When in planning the schedule, should I
simply design in the steps for either decision (go and no-go), and then when
tracking the decision actuals simply delete the follow-on tasks that were not
chosen?
Anyone who has used phase gates in MS Project I'd love to hear your thoughts
on this.