You need costed resources, and a baseline. You can always assign a
"Resource1" at $1/hr. Tasks must have an assigned Earned Value method of
Physical%Complete. You can do this be selecting all tasks, clicking the Task
Information icon, pull the advanced tab and change the EV method to
"Physical%Complete"
To assure all future entered tasks have Physical%Complete as their EV
method, you can change the default: Tools/Options.../Calculations (tab) and
click Earned Value... then select Physical%Complete
Consider changing your Gannt bars to reflect Physical%Complete
--