Plan Administrative Time 2007

R

Robert

Hello,
I clicked the Plan Administrative Time button in the My Timesheets page, so
that the Administrative Time dialog is open.
But sometime I'm able to enter time in the planned area, sometime I'm not.
What is the logic of this view?
Thanks
 
M

Marc Soester [MVP]

Robert, it depends on the admin task you have chosen. Within PRoject Server
you can request that admin tasks are approved by your timesheet manager
before you enter actual time ( e.g. Holiday ). Thats why you can enter
planned work on some admin tasks. Hope this helps
 