K
king kong
Hi all,
I have a, so it seems, simple question, but having tried various
parameters I cannot solve it myself.
I want to budget and plan a meeting, a workshop.
MS-Project 2003 (not server)
The meeting will last 8 hours.
4 People will participate. They all book their time on my project.
The daily rate is 1000 US$.
So the costs for this is 4000 US$.
So I added a task.
Said work: 8hrs, duration 1 day and added 4 resources 100%.
Which changes the duration to 0.38 days.
Does it mean I have to say: the work is 32 hours. Or can I somehow
configure or use MSP to do as I wish the way I wish.......
When I change it to fixed duration, allocate 24 hours of work and
give each resource 100%, then it seems to work. Is there a simpler way?
Thanks
Kay
I have a, so it seems, simple question, but having tried various
parameters I cannot solve it myself.
I want to budget and plan a meeting, a workshop.
MS-Project 2003 (not server)
The meeting will last 8 hours.
4 People will participate. They all book their time on my project.
The daily rate is 1000 US$.
So the costs for this is 4000 US$.
So I added a task.
Said work: 8hrs, duration 1 day and added 4 resources 100%.
Which changes the duration to 0.38 days.
Does it mean I have to say: the work is 32 hours. Or can I somehow
configure or use MSP to do as I wish the way I wish.......
When I change it to fixed duration, allocate 24 hours of work and
give each resource 100%, then it seems to work. Is there a simpler way?
Thanks
Kay