Portfolio Server - Resource budget - time-phased

N

Nickster

On portfolio server, I enter the number of resources required under a column
heading of "2009" for example, then I press "Resource to cost conversion". I
click on cost budget and it reflects the cost as "annual cost/12"; it
considers it a monthly cost. I need it to count it as yearly, where do I
cahnge the settings?

Thank you,

Nick
 
M

Mike Glen

Hi Nick,

Try posting on the microsoft.public.project.server newsgroup (forum).
Please see FAQ Item: 24. Project Newsgroups. FAQs, companion products and
other useful Project information can be seen at this web address:
http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 

Ask a Question