We have tasks in schedules that at some point in the project they no longer
are needed. For example a drawing is submitted for customer review. We have
tasks linked to the return of the submittal for any customer changes. So
times no changes are needed. Deleting these tasks has caused problems with
links to future tasks being deleted and not relinked. The causes tasks with
no links to be rescheduled to the project start date.
How do others handle this issue?
are needed. For example a drawing is submitted for customer review. We have
tasks linked to the return of the submittal for any customer changes. So
times no changes are needed. Deleting these tasks has caused problems with
links to future tasks being deleted and not relinked. The causes tasks with
no links to be rescheduled to the project start date.
How do others handle this issue?