D
DMM
Hi,
Let's say Developer 1 will work on task A from 12/1/2005 - 12/3/2005 and
Developer 2 will work on Task A on 12/1/2005 only. For Task B which
Developer 2 will start work on on 12/2/2005 can I use Task A as a predecessor
somehow? Currently, when I try to use Task A as a predecessor the start
date is 12/3/2005 instead of of 12/2/2005 which will be the first available
free date for Developer 2?
Do I have to not use predecessors in this situation or is there a way to do
it?
TIA,
DMM
Let's say Developer 1 will work on task A from 12/1/2005 - 12/3/2005 and
Developer 2 will work on Task A on 12/1/2005 only. For Task B which
Developer 2 will start work on on 12/2/2005 can I use Task A as a predecessor
somehow? Currently, when I try to use Task A as a predecessor the start
date is 12/3/2005 instead of of 12/2/2005 which will be the first available
free date for Developer 2?
Do I have to not use predecessors in this situation or is there a way to do
it?
TIA,
DMM