Hi Kristy123,
From the Calendar view, choose Format > Bar Styles. Select Noncritical
in the Task Type list. Towards the bottom change the fields(s)
information to read:
Name, Resource Names
Repeat for Critical tasks.
This will show the Task name and Resource Name(s) on the bar.
I hope this helps. Let us know how you get along.