I'm trying to create a chart that will show Priority work vs. regular work.
Is my first step to creating this, is to set my priority levels for each
tasks?

Is there a good learning tool for project that doesn't just give the basics?
 
D

DavidC

'Critical activities are those whose total slack is less than the number of
days slack considered to be critical as set under Tools/Options/Calculations.
Set the number of days in the lower box on the tab.

You may also need to format a bar style to identify critical tasks in
another colour.

Once you have set the days to be considered critical, then there is a filter
option under Project/Filtered for, called Critical. This filters out all
those tasks whose total slack is less than the days set as being considered
critical.

Hope this is what you are looking for.

Regards

DavidC
 