Problem with Master projects

L

Luis Calabria

I have tree projects. I need to publish the information, but I use a Master
Project to do that. So I put these tree projects into a Master Project and I
publish its information.

When a resource go to the View Task he see the normal task information.
The problem occurs when I replace the resource with another in one task. I
republish the information but the resource still have the task’s assignment.

In the traditional form (when I publish the specific project) the resource
see a X in the task when I change the assignment. In this case it doesn’t
occur.

In addition to this, when I reassign the resource to the task the resource
have two tasks instead of one.

I need to know, if this problem have a resolution.